Related Companies
|
[]
|
||||||||
Related Funds
|
[]
|
||||||||
English
|
|||||||||
oda_WinningATenderAbstract|
|
|
||||||||
oda_UpdateAnnouncementFlag|
|
|
Evet (Yes)
|
|||||||
oda_CorrectionAnnouncementFlag|
|
|
Hayır (No)
|
|||||||
oda_DateOfThePreviousNotificationAboutTheSameSubject|
|
|
30.11.2021
|
|||||||
oda_DelayedAnnouncementFlag|
|
|
Hayır (No)
|
|||||||
oda_AnnouncementContentSection|
|
|
||||||||
oda_SubjectOfTender|
|
|
Tender for additional investments to increase capacity of Antalya Airport and concessioning of the operating rights of the existing international terminal, CIP terminal, general aviation terminal, domestic terminal and their auxiliaries
|
|||||||
oda_PartyOpenedTender|
|
|
State Airports Authority (DHMI)
|
|||||||
oda_BoardDecisionOnBidForTender|
|
|
30.11.2021
|
|||||||
oda_OtherPartiesIfParticipatedInTheTenderAsAGroup|
|
|
Fraport AG Frankfurt Airport Services Worldwide
|
|||||||
oda_ShareOfTheCompanyIfParticipatedInTheTenderAsAGroup|
|
|
51%
|
|||||||
oda_DateOfTenderBid|
|
|
01/12/2021
|
|||||||
oda_EndingUpDateOfTheTender|
|
|
01/12/2021
|
|||||||
oda_TenderResult|
|
|
As the highest bidder, the joint venture formed by TAV and Fraport has won the tender.
|
|||||||
oda_TenderValue|
|
|
7.25 billion euros (VAT excluded)
|
|||||||
oda_ShareOfCompanyInTenderValue|
|
|
51%
|
|||||||
oda_RatioOfTenderValueCorporateShareAmountToGrossSalesRevenueOnPubliclyDisclosedTheLatestFinancialStatementOfCompany|
|
|
1.227
|
|||||||
oda_ExplanationSection|
|
|
||||||||
oda_ExplanationTextBlock|
|
As the highest bidder, the joint venture formed by TAV and Fraport (JV) has won the tender held by State Airports Authority (DHMI) for additional investments to increase capacity of Antalya Airport and concessioning of the operating rights of the existing international terminal, CIP terminal, general aviation terminal, domestic terminal and their auxiliaries. As per tender specifications, JV has the concession right to operate Antalya Airport for 25 years between the dates of January 1, 2027 and December 31, 2051. The current concession right held by TAV and Fraport partnership is valid until December 31, 2026.
The service charge will be 17 euros per outgoing international passenger and 3 euros per outgoing domestic passenger during the new concession period between January 1, 2027 and December 31, 2051. 7.25 billion euros (VAT excluded) will be paid as total concession rent to DHMI. An investment of circa 765 million euros is planned on EPC basis of which circa 600 million euros will be expended between 2022-2025 and circa 165 million euros will be expended between 2038-2040. More in-depth information is provided in the presentation attached.
The company that will be formed by JV will sign a lease contract with DHMI following the completion of necessary approvals and legal procedures.
|
We proclaim that our above disclosure is in conformity with the principles set down in “Material Events Communiqué” of Capital Markets Board, and it fully reflects all information coming to our knowledge on the subject matter thereof, and it is in conformity with our books, records and documents, and all reasonable efforts have been shown by our Company in order to obtain all information fully and accurately about the subject matter thereof, and we’re personally liable for the disclosures.