Related Companies
|
[]
|
||||||||
Related Funds
|
[]
|
||||||||
English
|
|||||||||
oda_NoncurrentAssetPurchaseAbstract|
|
|
||||||||
oda_UpdateAnnouncementFlag|
|
|
Evet (Yes)
|
|||||||
oda_CorrectionAnnouncementFlag|
|
|
Hayır (No)
|
|||||||
oda_DateOfThePreviousNotificationAboutTheSameSubject|
|
|
13.09.2022, 14.10.2022, 25.10.2022, 15.11.2022, 03.03.2023, 07.03.2023, 12.04.2023, 02.08.2023, 10.08.2023, 05.09.2023, 19.09.2023, 25.09.2023, 02.10.2023, 04.12.2023
|
|||||||
oda_DelayedAnnouncementFlag|
|
|
Hayır (No)
|
|||||||
oda_AnnouncementContentSection|
|
|
||||||||
oda_NatureOfNonCurrentAssetBought|
|
|
Energy Production Facility
|
|||||||
oda_LocationAndAreaofNoncurrentAssetBought|
|
|
-
|
|||||||
oda_BoardDecisionDateforPurchase|
|
|
06.12.2023
|
|||||||
oda_WereMajorityOfIndependentBoardMembersApprovedTheBoardDecisionForPurchase|
|
|
Yes
|
|||||||
oda_TotalPurchasingValue|http://www.xbrl.org/2003/role/verboseLabel
|
|
31.000.000 USD
|
|||||||
oda_RatioOfTransactionAmountToValueOfCompanyBasedOnTheMathematicalWeightedAverageOnADailyBasisSixMonthsPriorToDateOfBoardDecision|
|
|
%16
|
|||||||
oda_RationofPurchasePriceToPaidInCapitalOfCompany|
|
|
%342
|
|||||||
oda_RatioOfPurchasingValueToTotalAssetsinLatestDisclosedFinancialStatementsOfCompany|
|
|
%40
|
|||||||
oda_RatioOfPurchasingValueToTotalNetNoncurrentAssetsInLatestDisclosedFinancialStatementsOfCompany|
|
|
%161
|
|||||||
oda_RatioOfTransactionValueToSalesInLatestAnnualFinancialStatementsOfCompany|
|
|
%61
|
|||||||
oda_PurchasingConditions|
|
|
20% will be paid in cash and the remainder will be paid gradually.
|
|||||||
oda_DateOnWhichTheTransactionWasWillBeCompleted|
|
|
Ağustos 2025
|
|||||||
oda_AimOfPurchaseAndEffectsOnCompanyOperations|
|
|
It is expected to have a positive impact on turnover and profitability.
|
|||||||
oda_CounterParty|
|
|
Murel Yatırım İnşaat A.Ş.
|
|||||||
oda_IsCounterPartyARelatedPartyAccordingToCMBRegulations|
|
|
Hayır (No)
|
|||||||
oda_NatureofRelationWithCounterParty|
|
|
-
|
|||||||
oda_AgreementSigningDateIfExists|
|
|
06/12/2023
|
|||||||
oda_ExercisePriceOfRetirementRightRelatingToSignificantTransaction|
|
|
It is not a significant transaction within the scope of CMB legislation.
|
|||||||
oda_ValueDeterminationMethodOfNoncurrentAsset|
|
|
Negotiation Procedure
|
|||||||
oda_DidValuationReportBePrepared|
|
|
Düzenlenmedi (Not Prepared)
|
|||||||
oda_ReasonForNotPreparingValuationReportIfItWasNotPrepared|
|
|
-
|
|||||||
oda_DateAndNumberOfValuationReport|
|
|
-
|
|||||||
oda_TitleOfValuationCompanyPreparedReport|
|
|
-
|
|||||||
oda_ValueDeterminedInValuationReportIfExists|
|
|
-
|
|||||||
oda_ReasonsIfTransactionWasntWillNotBePerformedInAccordanceWithValuationReport|
|
|
-
|
|||||||
oda_ExplanationSection|
|
|
||||||||
oda_ExplanationTextBlock|
|
Our company and Murel Yatırım İnşaat A.Ş. will enter into force after the approval of our pre-license application numbered TLP-01401145, which we have made to the Energy Market Regulatory Authority (EPDK) for the pre-license permit of the power plant, which has been decided to be installed in the Konya Ereğli Paper Production Facility, the investment of which is ongoing. .S. A contract amounting to 31,000,000 USD (thirty-one million dollars) was signed between and for the installation, commissioning and testing processes of the Cogeneration Facility with a capacity of 37,650 MWh mechanical power (32 MWh electrical power), with the condition of commissioning in 21 months. This statement has been translated into English for informational purposes. In case of a discrepancy between the Turkish and the English versions of this disclosure statement, the Turkish version shall prevail. |
We proclaim that our above disclosure is in conformity with the principles set down in “Material Events Communiqué” of Capital Markets Board, and it fully reflects all information coming to our knowledge on the subject matter thereof, and it is in conformity with our books, records and documents, and all reasonable efforts have been shown by our Company in order to obtain all information fully and accurately about the subject matter thereof, and we’re personally liable for the disclosures.